Weekend Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmas50

PMI PfMP - Portfolio Management Professional (PfMP)

Page: 1 / 15
Total 495 questions

The governance role in oversight is abundant during planning in order to agree on multiple roles and responsibilities including those of a portfolio manager. The agreements are recorded in the meeting minutes and included as updates to

A.

Portfolio

B.

Portfolio Management Plan

C.

Portfolio Reports

D.

Portfolio Process Assets

Your portfolio has encountered a big issue and multiple management decisions have been taken in order to re-align the portfolio with the strategic objectives. What is the tool that you use in order to report major risks and issues to stakeholders?

A.

Portfolio Management Plan

B.

Portfolio Risk Register

C.

Portfolio Reports

D.

Portfolio Status Reports

You have been assigned as the manager for a major transformation portfolio in your company. You have a new direction in sight and you need to work with the team to attain the end goal and achieve the expected strategy. For this you start by developing the strategic plan. What output do you expect from this process?

A.

Portfolio, Portfolio Strategic Plan

B.

Portfolio, Portfolio Strategic Plan, Portfolio Reports

C.

Portfolio, Portfolio Strategic Plan, Enterprise Environmental Factors updates

D.

Portfolio Process Assets updates, Inventory Of Work, Portfolio, Portfolio Strategic Plan

In managing strategic change, the portfolio manager performs stakeholder analysis in order to consider the changing requirements. Which of the following options is referenced in this case to provide guidance on the communication required to ensure successful change?

A.

Portfolio Strategic Plan

B.

Portfolio Management Plan

C.

Portfolio Roadmap

D.

Portfolio Charter

Values assist in guiding actions, evaluations, and decisions. Assume your organization is considering entering into a consortium to produce a heliumcontrolled car. Once the helium is supplied, additional amounts will not be needed. The car is to be personally appealing with a focus on an inexpensive cost to increase marketability. The consortium will enable each firm to capitalize on the expertise of the other firms in it, but the customer will view it as a separate entity. If your organization enters into the consortium, it must justify the value to the portfolio of doing so. In addition to ensure benefits are realized a focus is needed on:

A.

Organizational value

B.

Sustainable value

C.

Managerial value

D.

Employee value

After the stakeholder analysis is complete, a best practice is to put stakeholders into a matrix to develop a communications management strategy. A simple but useful approach is to set it up to show:

A.

Level of authority and level of interest

B.

Level of authority and level of involvement

C.

Level of influence and level of impact

D.

Level of influence and level of interest

You are currently creating portfolio scenarios (what-if analysis) by reviewing components against prioritization criteria and using analysis techniques (e.g., options analysis, risk analysis, SWOT analysis, financial analysis). You are doing this in order to

A.

Understand the strategic priorities

B.

Create a basis for decision making

C.

Evaluate and select viable options

D.

Provide a guiding framework to operationalize the organizational strategic goals and objectives

Along the course of the portfolio, you will be recommending the initiation, termination and update of components. The governance bodies will be approving or rejecting your recommendations as part of their role in the authorization of the portfolio. As a portfolio manager, which of the following, in your opinion, is the objective/purpose of the Authorize Portfolio Process?

A.

Make Governance Decisions

B.

Allocating resources to develop component proposals or execute portfolio components

C.

Create an up-to-date list of qualified portfolio component

D.

Balance the portfolio for performance and value delivery

Your organization, given the economic downturn in your country, decided to reduce its staff by 90% and outsource all operational activities including those of program and project managers and their teams. It has, however, retained the portfolio manager, and it has a Portfolio Review Board comprised of senior executives that meets monthly. Since outsourcing is the norm and not the exception, the manager of Procurement and Contracting is a major stakeholder. Her areas of interest are:

A.

Benefits and outcomes toward strategic goals

B.

Overall portfolio performance

C.

Financial standing

D.

Change decisions

There was a change in your portfolio to speed up things resulting in the addition of new components. In order to update the new vision, dependencies and timeline for the components, you should update which of the following?

A.

Portfolio Roadmap

B.

Portfolio Charter

C.

Portfolio Strategic Plan

D.

Portfolio Management Plan