During the Managing a Stage Boundary process what product is updated with estimated costs and time for the stage that is about to begin?

A.

End Stage Report

B.

Team Plan

C.

Work Package

D.

Project Plan

Which is a purpose of the Starting up a Project process?

A.

Provide information so a decision can be made as to whether a project is viable and worthwhile to initiate

B.

Define the means of communication between the project and corporate or programme management

C.

Define the project controls

D.

Record any identified risks in the Risk Register

Which is a minimum requirement for applying the business case theme?

A.

To provide statements of actual benefits at benefits reviews

B.

To report on project performance at project closure

C.

To define the actions required to confirm the project's benefits are realized

D.

To monitor changes to the project plan to identify exceptions

What should the 'managing product delivery' process ensure?

1. That the planned products meet their quality criteria

2. That the stage plan is kept up to date

3. That the project board is provided with progress information

4. That the planned products are delivered within tolerance

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Identify the missing words in the following sentence. A risk budget is a sum of money included in the [ ? ] and set aside to fund specific management responses to a project's threats and opportunities.

A.

change budget

B.

project budget

C.

project's cost tolerance

D.

project's risk tolerance

Which of the following refers to the actions identified to bring a situation to a level where exposure to a risk is acceptable?

A.

Risk category

B.

Risk description

C.

Risk response

D.

Risk status

Which PRINCE2 principle is being applied when tolerances are set for the three levels of plan?

A.

Manage by stages

B.

Manage by exception

C.

Continued business justification

D.

Learn from experience

Which level of management sets the project level tolerances?

A.

Project board

B.

Team manager

C.

Corporate, programme management or the customer

D.

Project manager

Which product is created in the 'starting up a project' process to define and confirm the scope of the project?

A.

Project mandate

B.

Initiation stage plan

C.

Project initiation documentation

D.

Project brief

Which is an objective of the 'starting up a project' process?

A.

To approve the initiation stage

B.

To select the project mandate

C.

To define the project quality management approach

D.

To appoint the project management team