Summer Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: ecus65

PRINCE2 Prince2-Foundation - PRINCE2 7 Foundation written Exam

Page: 13 / 14
Total 461 questions

Which describes a characteristic of a project?

A.

It maintains business as usual profitability

B.

It provides a quality service to customers

C.

It involves a team with different skills

D.

It enables established and proven best practices

Identify the missing words in the following sentence.

The 'directing a project' process starts when [ ? ] and is triggered by the request to initiate a project.

A.

the 'starting up a project' process is completed

B.

the project mandate has been approved by the project board

C.

the project board has agreed the project strategies

D.

corporate, programme management or the customer have authorized a project

Which process ensures that key roles and responsibilities are allocated before a decision is made to initiate a project?

A.

Managing Product Delivery

B.

Initiating a Project

C.

Managing a Stage Boundary

D.

Starting up a Project

What action is taken as part of the 'controlling a stage' process?

1. Create an exception plan

2. Authorize work to be done

3. Take corrective action

4. Obtain approvals for completed products

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Which theme verifies that a project's products are fit for purpose?

A.

Business case

B.

Organization

C.

Quality

D.

Progress

Which describes an off-specification?

A.

An interdependency between products that was previously unidentified

B.

The addition of an improvement to a product description

C.

A prototype demonstrating a possible design solution

D.

The production of more than the defined quantity of a specialist product

Which is a purpose of the 'closing a project' process?

A.

To provide the project board with information to judge the success of a stage

B.

To confirm the project has nothing more to deliver

C.

To establish mechanisms to judge whether the project is still viable

D.

To establish mechanisms for forecasting project objectives

Which is a purpose of the 'controlling a stage' process?

A.

To produce a team plan for the work to be assigned to a team manager

B.

To select and implement actions that will resolve deviations from a plan within tolerance

C.

To obtain approvals for products delivered in a work package

D.

To update a project plan to incorporate the actuals from a stage plan

Which are benefits of using PRINCE2?

1. It removes the need for activity-based planning

2. It promotes learning and continuous improvement

3. It can be applied to any type of project

4. It defines specific leadership and other interpersonal skills required

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Identify the missing word in the following sentence.

The PRINCE2 method addresses project management with four integrated elements: principles, themes, [ ? ] and tailoring PRINCE2 to the project environment.

A.

activities

B.

processes

C.

products

D.

quality