An ICT distribution designer working for the owner receives a submitted product that differs from the product specified in the contract documents. The original product is unavailable due to shipping or manufacturing delay. Which action should the ICT distribution designer take?

A.

Reject the submittal after verifying compliance with applicable standards.

B.

Approve the submittal after asking about additional compensating warranty offerings.

C.

Approve the submittal after verifying code compliance.

D.

Approve the submittal after verifying all significant features of the originally specified product are met.

A global communications company's cloud-based platform will host its video network using both on - and off-shore learns. The program management office (PMO) assigns a program manager with little experience executing global initiatives.

What should the program manager do to resolve competing resource needs within components that could impact the entire program's overall delivery date?

A.

Require project managers to perform resource levelling in their schedules to automatically take into account availability and dependencies tor key resources.

B.

Revisit assignments on a weekly basis to manually level resources thereby limiting burn-out and preventing underutilization

C.

Optimize integration of the component projects by working with the project managers to align resource skill sets and availability to the program

D.

Improve communications between the project managers to gain efficiencies in resource assignments

In a RFI, an ICT distribution designer instructs the contractor to test all the fibers In a PON Installation. Which of the following testing requirements does the designer include?

A.

Uni-directional 850 nm and 1300 nm

B.

Bi-directional 850 nm and 1300 nm

C.

Uni-directional 1310 nm and 1550 nm

D.

Bi-directional 1310 nm and 1550 nm

Several issues are identified on one component project in a program During a meeting with that component's project manager, the program manager offers several suggested resolutions Two weeks later, they meet again to review progress The project manager had reviewed the issues and suggested resolutions, but delayed a decision. This two-week delay in taking action caused delays in the project schedule

What should the program manager do?

A.

Join project-level issue resolution meetings to accelerate the decision-making process.

B.

Initiate discussions with the program governance board about assigning a more experienced project manager to the project

C.

Emphasize that the project manager needs to address the issues and follow up at the next scheduled meeting

D.

Develop an immediate corrective action plan with the project manager and coach them on decision-making responsibilities

Before working on equipment, what is the FINAL step in the lockout/tagout (LOTO) procedure?

A.

Verify the equipment controls are in the proper operating position.

B.

Train workers to perform the LOTO process.

C.

Apply appropriate tags both locally and remotely.

D.

Confirm the device is de-energized by proving it will not run when started.

E.

Confirm all unnecessary items have been removed from the area.

In an office area, a consultant needs to add the location of a fax machine to the plan. What is the approximated floor area that a fax machine occupies?

A.

0.2 sq m (2 sq ft)

B.

0.5 sq m (5 sq ft)

C.

1 sq m (10 sq ft)

D.

1.5 sq m (16 sq ft)

E.

2 sq m (20 sq ft)

A program manager evaluates conflicting stakeholder demands associated with cost, schedule, and intended benefits. The implementation team has a strong interest in cost and schedule, and a limited interest in the benefits being produced. The client is only focused on benefits.

Which of the following actions should the program manager take?

A.

Focus on the internal stakeholders to ensure cost and) schedule objectives are achieved

B.

Balance stakeholder needs through the use of trade-offs among the stakeholder groups

C.

Focus on the external stakeholders to ensure the intended benefits are achieved

D.

Conduct a stakeholder meeting to allow everyone to state their priorities

Which of the following statements Is CORRECT concerning best practice for horizontal cable management panels?

A.

One RU of management panel for each RU of cable patch panel plus one additional RU of cable management

B.

Two RU of cable management panel for each RU of patch panel

C.

Three RU of cable management panel for each RU of patch panel

D.

Two RUs of management panel for each RU of cable patch panel plus two additional RUs of cable management

During a program's definition phase, it is determined that the best approach for delivering the programs intended benefits is to supplement corporate resources with the procurement of specific products and services from external suppliers. The program manager should use which of the following to determine and/or document the results of the program procurement planning activity?

A.

Make of buy decisions, alternatives analyses approach to competition, and best mix of contract types

B.

Requests for proposals (RFPs), proposal evaluation criteria, contract management and best mix of contract types

C.

RFPs. alternatives analyses, approach to competition, and requests for quotes (RFQs)

D.

Make-or-buy decisions, proposal evaluation criteria contract management, and RFQs

What is the MINIMUM lighting requirement (or telecommunications spaces?

A.

50 lux (4.6 toot-candles) of lighting in the horizontal plane and 20 lux (1.9 fool-candles) of lighting in the vertical plane measured al at 1 meter (3.28 feet) above the finished floor

B.

200 lux (18 6 fool-candles) of lighting In the horizontal plane and 500 lux (46 foot-candles) of lighting In the vertical plane measured at at 1 meter (3.28 feet) above the finished floor

C.

500 lux (46 foot-candles) of lighting in the horizontal plane and 200 lux (18 6 foot-candles) of lighting in the vertical plane measured at at 1 meter (3 28 feet) above the finished floor

D.

500 lux (46 foot-candles) of lighting in the horizontal plane and 500 lux (46 foot-candles) of lighting in the vertical plane measured at at 1 meter (3 28 feet) above the finished floor