BICSI RCDDv14.1 - BICSI Registered Communications Distribution Designer - RCDDv14.1
An ICT distribution designer working for the owner receives a submitted product that differs from the product specified in the contract documents. The original product is unavailable due to shipping or manufacturing delay. Which action should the ICT distribution designer take?
A global communications company's cloud-based platform will host its video network using both on - and off-shore learns. The program management office (PMO) assigns a program manager with little experience executing global initiatives.
What should the program manager do to resolve competing resource needs within components that could impact the entire program's overall delivery date?
In a RFI, an ICT distribution designer instructs the contractor to test all the fibers In a PON Installation. Which of the following testing requirements does the designer include?
Several issues are identified on one component project in a program During a meeting with that component's project manager, the program manager offers several suggested resolutions Two weeks later, they meet again to review progress The project manager had reviewed the issues and suggested resolutions, but delayed a decision. This two-week delay in taking action caused delays in the project schedule
What should the program manager do?
Before working on equipment, what is the FINAL step in the lockout/tagout (LOTO) procedure?
In an office area, a consultant needs to add the location of a fax machine to the plan. What is the approximated floor area that a fax machine occupies?
A program manager evaluates conflicting stakeholder demands associated with cost, schedule, and intended benefits. The implementation team has a strong interest in cost and schedule, and a limited interest in the benefits being produced. The client is only focused on benefits.
Which of the following actions should the program manager take?
Which of the following statements Is CORRECT concerning best practice for horizontal cable management panels?
During a program's definition phase, it is determined that the best approach for delivering the programs intended benefits is to supplement corporate resources with the procurement of specific products and services from external suppliers. The program manager should use which of the following to determine and/or document the results of the program procurement planning activity?
What is the MINIMUM lighting requirement (or telecommunications spaces?