BICSI RCDDv14 - BICSI Registered Communications Distribution Designer – RCDDv14
An organization initiates an innovation program to deliver exceptional performance and benefits. After the program transition plan is in place and the implementation of a benefits sustainment plan starts the program manager discovers the program may be shut down due to lack of funding.
To ensure continued funding for the program, what should the program manager do next?
When sizing an underground entrance facility, what is the MINIMUM amount of 103 metric designator conduits (4 trade size) that should be specified by the ICT distribution design?
When considering pathway types, the ICT distribution designer should consider the applicable MICE factors as defined in TIA 568 for structured cabling systems and components MICE 3 relates to
In a budding with one join room for serving as the FR and EF and four dedicated TRs on the same floor a total of__________ 103 mm (4 trade size) conduits should be installed to interconnect the backbone pathways to the ER.
A voice over IP network that converges voice capabilities with softphones. Video communications, instant messaging is referred to as
XYZ Company hires you to make its transitioning procedure more effective in meeting close-out requirements. You review XYZ's transitioning procedures to eliminate any that do not belong in the close-out phase.
Which of the following procedures should you removed?
A component is scheduled to close at the end of the week. What should the program manager verity prior to allowing the component to close?
A program manager is responsible for constructing a USS50 million building Management suggests it will take three years to complete The program manager can select a design-build option to optimize the construction schedule to 1 5 years However heavy demand for steel is causing price increases and delivery delays. II this trend continues, it could take as long as 4.5 years to complete construction. You learn that a new technology can yield a definitive delivery schedule of 1 25 years
What is the expected time of delivery?
During the program execution stage the component project manager responsible for testing estimates that budgeted hours may exceed 200 hours. What should the program manager do?
During the execution phase of a program a stakeholder complains to the program manager that they did not receive critical communications about one of the component projects What should the program manager do to address the situation'?