Which of the following is the process of limiting fire and smoke using fire-resistive barriers?

A.

Detection

B.

Compart mentation

C.

Suppression

D.

Prevention

A program manager has been assigned to a program that has received approval of the program charter and for which a stakeholder register has been prepared. During stakeholder engagement planning the program manager should consider which of the following stakeholder aspects?

A.

Attitude about the program external political position and technical expertise

B.

Level of influence and participation and attitude about the program

C.

Expectation of program benefits, level of influence, and organizational culture

D.

Level of support/opposition technical expertise, and organizational culture

A project's closeout plan will be executed by the project manager (PM) and will be managed and approved by the

A.

owner

B.

contractor

C.

lCT distribution designer

D.

projects installation supervisor

Telecommunications systems typically combine multiple digital data streams into one data stream. What is this process called?

A.

Time division multiplexing (TDM)

B.

Wave division multiplexing (WDM)

C.

Coarse wave time division multiplexing (CWTDM)

D.

Coarse wave division multiplexing (CWDM)

External resources are required for a program. The program manager receives bids from multiple vendors and presents the top vendor to the program governance board. One program governance board member asks the program manager to select a vendor that was dismissed early in the selection process because they were not on the approved vendor list The program manager learns that this program governance board member has a personal connection to this vendor

What should the program manager do?

A.

Add the vendor to the approved list

B.

Report an ethics violation

C.

Agree to engage the vendor due to the program governance board member's program influence

D.

Initiate a new vendor selection bid process

Component project managers create project management plans for all component projects in a program. The program manager notices that some project managers prefer one status report template while others prefer another

How should the program manager decide which template is appropriate?

A.

Review the issue with the program management office (PMO) to determine which template to use

B.

Review the issue with the project managers and come to mutual agreement on which template to use

C.

Meet with the program governance board to select an appropriate template

D.

Allow the component project managers to use their preferred templates

You have just finished a design calling for 15 telecommunications outlets. You received word that the owner has increased his requirements by 40%. What size commercial DD (distribution device) is required to accommodate the increase?

A.

660 mm (26 in)

B.

1015 mm (40 in)

C.

1346 mm (53 in)

D.

1676 mm (66 in)

Which service is NOT typical of Grade 1?

A.

Telephone

B.

Multimedia

C.

Data

D.

Television

A program manager notices that one project manager tends to withdraw during important team discussions to avoid conflict. What technique could the program manager use to gam more input from this project manager?

A.

Institute an incentive program to create competition among the team members.

B.

Make the project manager share an office with a more assertive team member

C.

Solicit ideas from each team member individually, giving each person a chance to express their opinions

D.

Create an online message board so team members can see and respond to everyone's ideas

A program manager has a multiple-project program that is scheduled to be completed by year's end. During the program delivery phases of the protects several mandatory changes are identified that would extend the program's completion date

What is the next step for the program manager?

A.

Apply resource leveling to ensure the program is completed on schedule

B.

Update the schedule to reflect the extended completion date

C.

Adjust working hours to ensure the program is completed on schedule

D.

Submit a change request to extend the program schedule