A program manager is identifying and verifying risks as outlined in the risk management plan. The results will be recorded in which of the following?

A.

Risk register

B.

Risk monitoring and control

C.

Risk response planning

D.

Risk mitigation strategy

The project manager of project A develops a communications management plan. The project manager of project B is new and is uncertain how to develop appropriate communications for the company's staff

What should the program manager do to ensure communications on the component projects are consistent?

A.

Request a more experienced project manager to work on project 6

B.

Create a program communications management plan across all component projects

C.

Direct all projects to use project A's communications management plan as a template

D.

Rework the communications management plans for all projects to be consistent

ICT project installation issues that require coordination with mechanical, electrical and/or other "trades" can be BEST accomplished by

A.

coordinating with the job site supervisors

B.

issuing an RFI to the General/Prime Contractor

C.

texting or calling the General/Prime Contractor

D.

issuing a Change Order

A large program consists of several component projects and six project managers. The program governance board requests that all components within the program undergo user acceptance testing before being released to the production environment

Where should the program manager document this?

A.

Program governance plan

B.

Program requirements

C.

Component test plan and test cases

D.

Program quality management plan

A program with objectives trial impact a large segment of the population receives negative commentary from organizations representing the public interest What action should the program manager take first?

A.

Rework the stakeholder engagement plan to foster better relationships with the affected stakeholder groups

B.

Review the stakeholder register to determine the ability of the affected stakeholder group(s) to affect program outcomes

C.

Assess the risk of sustained negative media coverage

D.

Discuss the issues with the governance board to determine next steps

A hotel chain initiates a program to expand meeting offerings to include telecommunications technology and virtual meetings. The program has component projects, each of which requires team members to have different technical skills and expertise. The program manager assembles a team of project managers to lead each of the projects, and learns that the desired resources will not be available at the start of the program

As a result, the program manager must do which of the following'?

A.

Utilize team members that are currently available, even though they do not have the expertise needed.

B.

Assign the tasks on the critical path to the resources available to adhere to the project schedule

C.

Delay the start of the program until the assigned resources are available

D.

Apply resource leveling considering the constraints of time, budget, and quality