Scrum SMC - Scrum Master Certified (SMC)

Page: 1 / 5
Total 147 questions

All of the following events and activities are examples of adaptation, EXCEPT:

A.

Seeking help from team members

B.

Experienced team members mentoring new members

C.

Recording Lessons learned to improve processes and address problems

D.

Using information radiators to track the project progress

Collaboration within a team is an important principle of Scrum. All of the following activities constitute

collaboration EXCEPT:

A.

The Scrum Team decides which User Stories are important and assigns which Sprint they should be

worked on.

B.

The Scrum Team discusses the best approach to creating deliverables during a Sprint.

C.

A Scrum Team member is facing difficulties in one of his tasks and another team member pitches in to

help him.

D.

The Scrum Team interacts with the Product Owner to obtain clarification on User Stories.

It is not allowed to change the members of the Development Team.

A.

True

B.

False

You are the Scrum Master for your organization and Sally is the Product Owner. The Development Team approaches you with many questions regarding a user story. What should you do next in this scenario?

A.

The Development Team should work with you as this is roadblock.

B.

The Development Team should meet with Sally to determine clarity on the user story, to determine what is possible, and what is acceptable.

C.

The Development Team and Sally should determine which Development Team member(s) should speak with the customer owning the requirement.

D.

The Development Team should determine which Development Team member(s) should speak with the customer owning the requirement.

A large software company has 8 Scrum teams with each team having a Scrum Master. After the Daily Standup

everyday with their respective teams, all Scrum Masters meet for a Scrum of Scrums. What are they likely to

do during this meeting?

A.

Discuss ways to resolve technical impediments faced by development teams, especially if two or more

teams face the same issue.

B.

Discuss what each individual development team member has worked on since the last time all Scrum

Masters met.

C.

Discuss actions of a team that could potentially affect another team.

D.

Share a status update on all individual team member' tasks.

Program Stakeholders, the Program Product Owner, Program Scrum Master, and Chief Product Owner have

gathered together to create the Project Vision. They are trying to determine and document the difference

between current business capabilities and the final desired set of capabilities. Which one of the following

should they use to arrive at a conclusive decision?

A.

Trial Project.

B.

JAD Session.

C.

Gap Analysis.

D.

SWOT Analysis.

A representative of the customer has asked the Development Team to add a very important item to an ongoing Sprint. What should they do?

A.

Refer the representative to the Scrum Master to discuss it

B.

Accept it only if they are willing to ask for it formally

C.

Refer the representative to the Product Owner to discuss it

D.

Refuse it, because they are in the middle of the Sprint

Which of the following are important selection criteria while choosing a Scrum Master?

A.

Leadership style, problem-solving, availability, commitment

B.

Stress management, people management, communication, loyalty

C.

Responsiveness, problem-solving, facilitator, negotiation

D.

Intuitiveness, people management, reliability, facilitator

Gary, a Development Team member, wants to know how long a Daily Scrum is. What's the timebox for a Daily Scrum?

A.

4 hours or less

B.

15 minutes

C.

2 hours

D.

1 hour

All of the following statements about Risk Communications are true, EXCEPT:

A.

The Stakeholders should be continuously informed about risks, including the potential impact of these risks

and the plans for responding to each risk.

B.

The Scrum Team may also discuss specific risks related to their Tasks with the Product Owner during

Daily Standup Meetings.

C.

The Product Owner is responsible for the prioritization of risks and for communicating the prioritized list to

the Scrum Team.

D.

Information related to risks is maintained and updated through the Risk Burndown Chart.