Which of the following statements regarding formal and/or informal assessment is FALSE?

A.

Formal TMMi assessments must be led by an accredited TMMi lead assessor.

B.

Both formal and informal TMMi assessments will provide an official result on test process maturity.

C.

Informal assessments require only one type of evidence.

D.

Both formal and informal assessment will provide a list of strengths and weaknesses of an organization against the TMMi model.

Which of the following statements about the Acting phase of the IDEAL improvement model is TRUE?

A.

This phase normally consumes the least effort in the IDEAL process, at about 15% of the total.

B.

“Develop approach” and “Create solution” are activities in this phase.

C.

“Plan actions” and “Implement solution” are activities in this phase.

D.

“Create solution” and “Implement Solution” are activities in this phase.

Which of the following is an Agile practice that can be applied as a way to establish a test strategy (SG2) within the Test Policy and Strategy process area?

A.

Testing quadrants

B.

Velocity

C.

Release planning

D.

Definition-of-done

How do TMMi based organizations benefit from the Agile way of thinking?

A.

Within Agile test improvements will typically take place through an organization-wide Test Process Group that can take rapid action

B.

By using TMMi as a reminder of critical testing practices that are often not defined or "forgotten" in Agile development methodologies

C.

The Agile way of thinking typically brings out the initiative to further detail the test processes as they are currently defined

D.

By only focusing on team-based related test process areas, and omitting anything that is related to improving testing at an organizational level.

Within the Generic Goals, TMMi distinguishes between two levels of institutionalization: a managed process (Generic Goal 2) and a defined process (Generic Goal 3).

Which of the following statements is NOT related to a managed process (Generic Goal 2|?

A.

It is tailored from the organization's set of standard processes according to the organization's tailoring guidelines

B.

The process that accomplishes the work necessary to produce work products.

C.

it is planned and executed in line with a policy

D.

It involves relevant stakeholders, is monitored and controlled.

What is an example of an indirect benefit for a test improvement program?

A.

Improvement in staff motivation

B.

Shortened lead-time of test execution phase

C.

Higher levels of defect detection

D.

Improved (more reliable. test estimations

To which TMMi level do the process areas Test Organization and Test Training Program belong?

A.

TMMi level 2 Managed

B.

TMMi level 3 Defined

C.

TMMi level 4 Measured

D.

TMMi level 5 Optimization

Which of the following statements is TRUE regarding relevance of the CMMI model version 2 for testing?

A.

The CMMI version 2 acknowledges that it is focused on software development only and therefore does not at all address testing

B.

The CMMI version 2 contains (he Peer Reviews practice area, but no other dedicated testing process areas

C.

The CMMI version 2 contains two dedicated practice areas for testing Verification and Validation

D.

The continuous representation of CMMI version 2 allows for a capability level determination of the software testing prractice areas Peer Reviews and Verification & Validation

The objective of a process area is to measure product quality early in the lifecycle, to enhance the test strategy and test approach by aligning static testing with dynamic testing, and to use the static testing results and data to optimize the test approach.

Which of the following process areas is concerned with this objective?

A.

Peer Reviews

B.

Product Quality Evaluation

C.

Advanced Reviews

D.

Test Measurement

Test Planning is identified as one of the process areas at TMMi level 2. It introduces practices such as perform product risk analysis, define test approach, establish test estimates and obtain commitment to the test plan. TMMi process areas at higher TMMi levels build on these practices.

Which of the following TMMi level 3 process areas most strongly and specifically builds on the practices and experiences of Test Planning at TMMi level 2?

A.

Test Organization

B.

Test Lifecycle and Integration

C.

Non-Functional Testing

D.

Peer Reviews